| Housing Quality Standards
Housing Quality Standards (HQS) are the HUD minimum quality
standards for tenant-based programs. HQS standards are required
both at initial occupancy and during the term of the lease.
HQS standards apply to the building and premises, as well
as the unit. Newly leased units must pass the HQS inspection
before the beginning date of the assisted lease and HAP contract.
Guidelines/Types Of Inspections
Efforts will be made at all times to encourage owners to
provide housing above HQS minimum standards. Owners are responsible
for maintaining housing that will continuously meet the minimum
HQS standards and acceptance of a rental assistance payment
from CH constitutes compliance.
All utilities must be in service prior to the effective
date of HAP contract. If the utilities are not in service
at the time of inspection, the Inspector will notify the
tenant or owner (whomever is responsible for the utilities
according to the RFTA) to have the utilities turned on. The
Inspector will schedule a re-inspection. The owner and tenant
will both certify that the utilities are on.
If the tenant is responsible for supplying the stove and/or
the refrigerator, CH will allow the stove and refrigerator
to be placed in the unit after the inspection, if after the
unit has passed all other HQS, the family certifies that
the appliances are in the unit and working according to the
Housing Quality Standards. CH will not conduct a re-inspection.
There are five types of inspections CH will perform:
1. Initial/Move-in: Conducted upon receipt of Request For
Lease Approval.
2. Annual: Must be conducted prior to HAP contract anniversary
date.
3. Special/Complaint: At request of owner, family or an
agency or third-party.
4. Quality Control
Initial HQS Inspection
CH will make every reasonable effort to conduct initial HQS
inspections for the family and owner in a manner that is
time efficient and indicative of good customer service.
The Initial Inspection will be conducted to:
Determine if the unit and property meets HQS.
Document the current condition of the unit as to assist
in future evaluations whether the future condition of the
unit exceeds normal wear and tear.
If the unit fails the initial Housing Quality Standards
inspection, the owner will be advised to notify CH once repairs
are completed.
On an initial inspection, the owner will be given up to
30 days to correct the items noted as Fail, at the Inspector's
discretion, depending on the amount and complexity of work
to be done.
If the time period given by the Inspector to correct the
repairs has elapsed, or the maximum number of failed re-inspection
has occurred, the family must select another unit assuming
the Voucher has not expired.
Annual HQS Inspections
CH conducts an inspection in accordance with Housing Quality
Standards at least annually, 90 days prior to the anniversary
month of the contract. Special inspections may be scheduled
between anniversary dates.
The landlord must correct HQS deficiencies that cause a
unit to fail unless it is a fail for which the tenant is
responsible.
The family must allow CH to inspect the unit at reasonable
times with reasonable notice.
The family and owner are notified of the date and approximate
time of the inspection appointment .
Time Standards for Repairs
1. Emergency items that endanger
the family’s health
or safety must be corrected by the owner within 24 hours
of notification.
2. For non-emergency items, repairs must be made within
30 days.
3. For major repairs, the Director of Leased Housing may
approve an extension beyond 30 days.
Rent Increases
CH will conduct an inspection using the Housing Quality
Standards at least annually, prior to the anniversary month
of the contract. Contract rent increases will not be approved
if the unit is in a failed condition.
Special/Complaint Inspections
If at any time the family or owner notifies CH that the
unit does not meet Housing Quality Standards, CH will conduct
an inspection.
CH may also conduct a special inspection based on information
from third parties such as neighbors or public officials.
Quality Control Inspections
Quality Control inspections will be performed by the Leased
Housing Program Specialists for the purpose of determining
if each inspector is conducting accurate and complete inspections,
and to ensure that there is consistency among inspectors
in application of the HQS.
The sampling of files will include recently completed inspections
(within the prior 3 months), a cross-section of neighborhoods,
and a cross-section of inspectors.
Consequences for HQS Non-Compliance
If Owner Is Responsible (Non-Emergency Items)
When it has been determined that a unit on the program fails
to meet Housing Quality Standards, due to the owner not having
completed the necessary repair(s) in the time period specified
by CH, the assistance payment to the owner will be abated
and a 30 day notice of termination of the HAP contract will
be sent to the owner and tenant.
Abatement
A Notice of Abatement will be sent to the owner informing
them of the abatement. The abatement period will coincide
with the termination period.
No retroactive payments will be made to the owner for the
period of time the rent was abated and the unit did not comply
with HQS. The notice of abatement states that the tenant
is not responsible for CH's portion of rent that is abated.
Termination of Contract
If the owner is responsible for repairs, and fails to correct
all the deficiencies cited prior to the end of the period
given by CH to make the repairs, the owner will be sent a
HAP Contract Termination Notice. The abatement period and
termination period will coincide.
If repairs are completed before the effective termination
date, the termination may be rescinded by CH if the tenant
chooses to remain in the unit. Only one Housing Quality Standards
inspection will be conducted after the termination notice
is issued.
Determination Of Responsibility
Certain HQS deficiencies are considered the responsibility
of the family:
- Tenant-paid utilities not in service.
- Failure to provide or maintain family-supplied appliances.
- Damage to the unit or premises caused by a household member
or guest beyond normal wear and tear.
The owner is responsible for all other HQS violations.
The owner is responsible for vermin infestation even if
caused by the family's living habits. However, if such infestation
is serious and repeated, it may be considered a lease violation
and the owner may evict for serious or repeated violation
of the lease. CH may terminate the family's assistance on
that basis.
The inspector will make a determination of owner or family
responsibility during the inspection.
If the family is responsible but the owner carries out the
repairs, the owner will be encouraged to bill the family
for the cost of the repairs and the family's file will be
noted.
Consequences If Family Is Responsible
If non-emergency violations of HQS are determined to be
the responsibility of the family, CH will require the family
make any repair(s) or corrections within 10 days. If the
repair(s) or correction(s) are not made in this time period,
CH will terminate assistance to the family. The Director
of Leased Housing must approve extensions in these cases.
The owner's rent will not be abated for items that are the
family's responsibility.
If the tenant is responsible and corrections are not made,
HAP Contract will terminate when assistance is terminated.
Lead Based Paint
Lead-based paint rules apply to all housing constructed
before 1978 and where a child under six years of age or a
pregnant woman will reside.
All tenants must be provided with
a copy of the HUD/EPA pamphlet “Protect Your family from Lead in Your Home”.
This document, EPA747-K-9401 is available through the Government
Printing Office. Photocopies are acceptable.) The owner and
family must complete and sign a “Disclosure of Information
on Lead-Based Paint and/or Lead-Based Paint Hazards”.
This form must be kept by the owner for at least three years.
The owner must disclose any known lead-based paint hazards
to the family.
CH must compete a visual assessment
for deteriorated paint during the initial and annual inspection.
(For more information
on lead-based paint in general, see the HUD and EPA web pages.
During inspections, all deteriorated or damaged paint will
be assumed to be lead-based paint (LBP) unless the paint
has been tested and cleared by a licensed Lead Inspector
or Risk Assessor. All deteriorated paint must be stabilized
by properly trained persons. Paint stabilization must be
completed before the unit is occupied or within 30 days of
notification if the unit is already occupied. (See CH’s
Lead Paint Guide)
Only properly trained persons may work on LBP or paint assumed
to be LBP. Clearance testing is required after repairing
LBP. At the completion of work involving LBP or paint assumed
to be LBP, the owner must have lead wipe samples secured
by a licensed lead inspector and the dust levels must be
below HUD defined levels. Section 8 will provide this service
at no charge to the owner.
If there is a child with an Elevated Blood Level (EBL) under
age six in the unit, a Lead Risk Assessment of the unit and
common areas must be completed within 15 days of notification.
(A child with an Elevated Blood Level is one determined to
have excess lead levels in the blood stream.) The assessment
may be performed by the Health Department.
|